A Construction Example of Pile Amending by Consolidation Grouting


XU Si fa The Second Bureau of Harbor and Channel Engineering,Wuhan 430014,China)

DOI:10.11835/j.issn.1674-4764.2001.05.017

Received ,Revised August 30, 2001, Accepted , Available online July 01, 2015

Volume ,2001,Pages 81-84

  • Abstract
In this paper the amendment of No.18 pile in 19th pier of Citong Bridge in Quanzhou city is presented. There is a soft layer 6.41m thick in No.18 pile,a site cast concrete pile,due to breakdown of guide tube during casting. Amended by consolidation grouting, the pile stood up to tests. The construction technology, adopted steps and test method were introduced. It can serve as reference to similar engineering.